Tuesday, 6 November 2012

Over the past 6 weeks we have taken the site from foundation level up to finished floor level. This included the completion of brickwork and blockwork to finished floor level and the installation the beam and block floor.

We then layed the gas barrier and floor insulation which means we can now pour the slab concrete on Block 1 tomorrow and Block 2 next Tuesday. We will also be assembling the scaffolding on Blocks 1 and 2 in the near future. Shortly after the Timber Frame will be erected on Block 1 and on Block 2 a few weeks later.