Tuesday, 18 December 2012

The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Foldings Avenue.

Our site will close for the Christmas period on Friday 21 December, and will re-open in the new year on Wednesday 2 January.

Can we also take this opportunity to wish you a merry Christmas and a happy new year!

Monday, 17 December 2012

Progress at Foldings Avenue has seen block 1 almost water tight with the exception of the external doors. Block 2 isn't too far behind, the timber frame is 75% complete with the balance due to be finished this week. The external works are also well advanced with 80% of the drainage installed and the first coat of tarmac laid to the road area. All in all we are on programme to have both blocks water tight before the Christmas break, which will enable us to commence the internal plastering work in January.