Progress at Foldings Avenue has seen block 1 almost water tight with the exception of the external doors. Block 2 isn't too far behind, the timber frame is 75% complete with the balance due to be finished this week. The external works are also well advanced with 80% of the drainage installed and the first coat of tarmac laid to the road area. All in all we are on programme to have both blocks water tight before the Christmas break, which will enable us to commence the internal plastering work in January.