Progress has been slow in January due to the adverse weather and cold temperatures, however February brings renewed vigour. The external masonry has now commenced to both blocks, all the windows and doors have been installed, likewise the roof is now fully in place, allowing for internal works to start.
The programme has been compromised because of the weather but we are hopeful of making this up on the internal works.